| Project: Thai Olefin Co.,Ltd. |
| Nature of the project |
Pentrochemical Plant |
| Type of the project |
Turn - Key |
| Location of the plant |
Royong Industrial Estate |
| Volume of the project |
200,000 R - T |
| Origin of main cargo |
Korea, Germany, USA, Japan |
| Extra heavy cargo |
1 Piece of Tower , Weight:558 Tons, Length :85 meters |
| Time of project |
3 Years |
| Main Contractor |
Daelim Engineering Co.,Ltd. , Seoul, Korea |
|
Project: National Petrochemical (Public)Co.,Ltd.
|
| Nature of the project |
Petrochemical Plant |
| Type of the project |
Turn - Key |
| Location of the plant |
Rayong Industrial Estate |
| Volume of the project |
120,000 R- T |
| Origin of main cargo |
Korea, Germany, USA, Japan |
| Extra heavy cargo |
1 Piece of Tower, Weight:200 Tones, Length:70 Meters |
| Time of project |
2 Years |
| Main Contractor |
Daelim Engineering Co.,Ltd. Seoul, Korea |
|
Project: Thai Clement Co.,Ltd.
|
| Nature of the project |
Tyre & Wheel |
| Type of the project |
Turn - Key |
| Location of the plant |
Sriracha Industrial Estate |
| Volume of the project |
30,000 R - T |
| Origin of main cargo |
Italy |
| Time of project |
3 Months |
| Main Contractor |
Michelin in Italy |
|
|